華星東方公司承建的廣東省汕頭市澄海潔源生活垃圾焚燒發電項目三期煙氣凈化工程于2021年09月10日通過72+24小時試運行。
The FGC project contracted by Huaxing-east for phase III of Chenghai Jieyuan waste-to-energy plant in Shantou, Guangdong passed 72+24 hours trial operation on Sept. 10, 2021.
該項目一、二期原有2x225t/d+1x320t/d三條焚燒線,本期新建規模1x750t/d+1x20MW汽輪機+1x22MW發電機。煙氣處理采用“旋轉霧化半干法脫酸+干法(碳酸氫鈉)脫酸+活性炭吸附+布袋除塵器+飛灰輸送、存儲及穩定化工藝”的煙氣凈化工藝,為我司EPC工程。
The phase I & II for the project have three incineration lines of 2x225 t/d and 1x320 t/d. Phase III built 1x750 t/d + 1x20 MW steam turbine + 1x22 MW generator. The FGC adopts the process of "rotary atomization semi-dry deacidification + dry deacidification with sodium bicarbonate + activated carbon adsorption + bag filter + fly ash conveying, storage and stabilization", which is an EPC project of Huaxing.
華星東方在廣東省的業績涵蓋包括:東莞駿業、汕頭潮南、普寧、惠陽、肇慶、汕頭澄海、高州、中山等多個項目。
The achievements of HXET in Guangdong Province include Dongguan Junye, Shantou Chaonan, Puning, Huiyang, Zhaoqing, Shantou Chenghai, Gaozhou, Zhongshan, etc.