華星東方承建的黑龍江省齊齊哈爾市克山生活垃圾焚燒發電項目煙氣凈化工程于2023年08月15日開工建設。
The flue gas cleaning project of Keshan household waste incineration power generation project in Qiqihar City, Heilongjiang Province, undertaken by our company, started construction on August 15, 2023.
該項目設計規模為日處理生活垃圾600噸,配置1x600t/d機械爐排爐。煙氣處理采用“SNCR(非本次合同范圍內)+SDA半干法+干法+活性炭噴射+布袋除塵器+飛灰輸送及儲存”的煙氣凈化工藝,為我司EPC工程。
The design scale of this project is to process 600tonnes of household waste per day, equipped with 1x600t/d mechanical grate furnaces. The flue gas treatment adopts the flue gas cleaning process of "SNCR (not within the scope of this contract)+SDA semi dry method+dry method+activated carbon injection+bag filter+fly ash conveying and storage", which is our EPC project.
華星東方在黑龍江省的業績涵蓋包括:七臺河、雞西、佳木斯、佳木斯樺南、鶴崗、綏化、齊齊哈爾、齊齊哈爾克山、哈爾濱巴彥等多個項目。
Huaxing East Co's performance in Heilongjiang Province includes multiple projects such as Qitaihe, Jixi, Jiamusi Huanan, Hegang, Suihua, Qiqihar, Qiqihar, Keshan, Harbin Bayan, etc.